Portfolio

Girder Delivery - St. Louis

About This Project

The structural steel for a new bridge over the South Saskatchewan River was being shipped to the construction site a few months in advance of when the girder erection work was scheduled to take place.  As a result Johnston Construction was brought out to receive and organize the structural steel girders for the General Contractor who was not yet onsite.  Johnston Construction mobilized a crew and equipment to the site on short notice, prepared the critical lift plans and provided engineering support for the temporary shoring.  By putting in some long hours and maintaining crew availability the erratic shipping schedule was accommodated and the 12’ tall girders were received quickly and efficiently.  The project was completed without incident for a very pleased client.

Location:
Prince Albert, Saskatchewan
Value:
$160,000


Principal Client:
Saskatchewan Department of Highwways and Transportation
Contact Name:
Jeff Nelson
Contact Position:
Senior Bridge Engineer
Scheduled Delivery:
Oct 10, 2013
Actual Delivery:
Oct 31, 2013
Reason for Delay:
Bridge Washout; Fluid Delivery Schedule
Services Provided:
Receive & Organize Structural Steel for Erection